UK renewable energy: the long wait for grid connections must end

0

For the Brits, queue-barging goes against the grain. But first-come-first-served is a poor way to manage the slew of renewable energy projects seeking a connection to the grid. With a backlog of 257 gigawatts, the queue is slowing the UK’s progress towards net zero. New applicants are receiving connection dates more than a decade into the future.

Getting a lot of renewables built and connected to the power grid is crucial if the UK is to reach its goal of net zero power by 2035. To date, some 83GW of low-carbon capacity — renewable and nuclear — has been connected, contributing almost half of the UK’s electricity in 2022. National Grid’s future energy scenarios suggest Britain needs 123-147GW by 2030. That implies a huge ramp-up in the rate of construction, especially for solar and offshore wind.

These numbers also suggest that there are more than three times as many projects in the holding pattern as are likely to be needed. Many exist in name only. The system operator, National Grid ESO, is alive to this problem. It has been trying to get zombies to leave the queue by removing the penalty to do so, and is working to speed up the current connections process. That is not likely to be enough.

Lex charts showing grid connection queues for wind and solar in select countries, and UK grid connections applications

To get projects up and running faster, one idea is to cherry pick the ones that are likeliest to get built. Octopus Energy has suggested the UK take a leaf out of Australia’s book, giving priority connections to projects that have their permitting and financing in place. The system operator might also highlight the areas in which it does have spare grid capacity so that keen developers can rush to build where they will not need to wait for network reinforcements.

Such queue-barging is unlikely to be popular with projects that already have connection dates. But other countries, such as Germany and France, already restrict applications to projects with all their paperwork in place. Australia, which used to have a system akin to the UK’s, has changed the rules. With such a monumental task ahead, the power system needs to break this gridlock.

Lex recommends the FT’s Due Diligence newsletter, a curated briefing on the world of mergers and acquisitions. Click here to sign up.

Stay connected with us on social media platform for instant update click here to join our  Twitter, & Facebook

We are now on Telegram. Click here to join our channel (@TechiUpdate) and stay updated with the latest Technology headlines.

For all the latest World News Click Here 

Read original article here

Denial of responsibility! Rapidtelecast.com is an automatic aggregator around the global media. All the content are available free on Internet. We have just arranged it in one platform for educational purpose only. In each content, the hyperlink to the primary source is specified. All trademarks belong to their rightful owners, all materials to their authors. If you are the owner of the content and do not want us to publish your materials on our website, please contact us by email – [email protected]. The content will be deleted within 24 hours.
Leave a comment